Identification of Techno Economically Viable Projects

Preparation of Prefeasibility and Bankable Detailed Project Reports:
 |
Reconnaissance |
 |
Hydrological investigations |
 |
Pre Feasibility study and reports |
 |
Project clearance assistance |
|
 |
Topographical survey and geological investigations |
 |
Environment related aspects |
 |
Detailed project report |
|

Project Implementation
 |
Detailed Engineering including bid evaluation and recommendations |
 |
Construction scheduling and project Management |

Due Diligence Studies
|

Site Supervision, Erection, Testing and Commissioning

Implementation, Wheeling of Power Purchase Agreements
 |
Expert advisory services on drafting and negotiations on agreements with concerned agencies like SEB’s, PGCIL etc. for arranging generation, transmission and wheeling, construction power etc., as well as Power Purchase Agreement. |
|
|
|

RMU/ RLA/ LE Studies for Hydropower Projects
|
ICCS HAS SUCCESSFULLY DESIGNED & ENGINEERED THE FOLLOWING PROJECTS:
|
|
|
|
|
S.No |
Project Developer |
Project |
Capacity in MW |
Year of Commissioning |
(A) |
HYDRO |
1 |
M/s HEG Ltd |
Tawa HEP Itarsi, MP |
13.5 |
1997 |
2 |
Malana Power Co Ltd. |
Malana HEP, Kullu, HP |
86 |
2001 |
3 |
M/s DLI Power (India) Private Limited |
Bhandardhara HEP
Nasik, Maharashtra |
14 |
2002 |
4 |
M/s Vidhyanchal Power Ltd. |
Vajra HEP, Thane, Maharashtra |
3 |
2002 |
5 |
M/s SEW Construction Ltd. |
Gangrel HEP, Raipur, Chattisgarh |
10 |
2004 |
6 |
M/s KKK Hydro Power Ltd. |
Baragran HEP, Kullu, HP |
4.9 |
2004 |
7 |
M/s SEW Construction Ltd. |
Rani Avanti Bai, Jabalpur, MP |
10 |
2005 |
8 |
M/s Himalayan Crest Power Ltd. |
Manal HEP, Sirmour, HP |
3 |
2005 |
9 |
M/s Ginni Global Ltd. |
Taraila HEP, Chamba, HP |
5 |
2007 |
10 |
M/s Himalayan Crest Power Ltd. |
Chandni HEP, Sirmour, HP |
3 |
2008 |
11 |
M/s Himalayan Crest Power Ltd. |
Timbi HEP, Sirmour , HP |
3 |
2009 |
12 |
M/s P&R Engineering Limited |
Brenwar HEP, J&K |
7.5 |
2009 |
13 |
Narmada Valley Development Authority |
Indira Sagar HEP, Khandwa, MP |
15 |
2010 |
(B) |
THERMAL |
14 |
M/s HEG |
Captive Power Plant, Mandideep. |
2 x 30 |
2005 |
15 |
M/s Maral Overseas Ltd. |
Captive Power Plant Khalbuzurg, MP |
1 x 10 |
2007 |
16 |
M/s RSWM |
Captive Power Plant
Mordi |
2 x 23 |
2008 |
17 |
M/s Grasim India Ltd. |
Captive Power Plant at Bhiwani |
1 x 8 |
2008 |
(C) |
WIND |
18 |
M/s BSL
M/s BMD |
Wind Power Plant, Installation of 7 Nos. Wind Electric Converters (WEC’s) in Jaiselmer, Rajasthan. |
4.2 |
2004 |
|
ICCS IS CURRENTLY OFFERING DESIGN & ENGINEERING SERVICES FOR THE FOLLOWING PROJECTS:
S.No |
Project Developer |
Project |
Capacity in MW |
1 |
M/s Bhilwara Energy Ltd. |
Nyamjung Chhu HEP Tawang, Arunachal Pradesh |
900 |
2 |
M/s A D Hydro Power Ltd. |
Allain Duhangan HEP, Kullu, HP |
192 |
3 |
M/s Jal Power Corporation Ltd. |
Rangit-IV HEP, Sikkim |
120 |
4 |
M/s Green Ventures Private Limited |
Likhu HEP, Nepal |
120 |
5 |
M/s Nuziveedu Seeds Limited |
Tidong HEP, Kinnaur, H.P. |
100 |
6 |
M/s Bhilwara Energy Ltd. |
UBDC, Stage-III, , Gurdaspur, Punjab |
85 |
7 |
M/s Coastal Projects Private Limited |
Pallivasal, Kerala |
60 |
8 |
M/s Balephi Jal Vidyut Company Limited |
Balephi HEP, Nepal |
50 |
9 |
M/s Nuziveedu Seeds Limited |
Tangnu Romai I, HP |
44 |
10 |
M/s Electrosteel Castings Limited |
Balason HEP, West Bengal |
24 |
11 |
M/s Kanchanjunga Power Co. Pvt. Ltd. |
Baragaon HEP, Kullu, HP |
24 |
12 |
M/s Signet Suppliers Pvt. Ltd. |
Kut HEP, HP |
24 |
13 |
M/s Uttar Bharat Hydro Power Pvt. Ltd. |
Sarju II HEP, Uttarakhand |
15 |
14 |
M/s Uttar Bharat Hydro Power Pvt. Ltd. |
Sarju III HEP, Uttarakhand |
9 |
15 |
M/s Uttar Bharat Hydro Power Pvt. Ltd. |
Sarju I HEP, Uttarakhand |
6 |
16 |
M/s Nuziveedu Seeds Limited |
Tangnu Romai II, HP |
6 |
17 |
M/s Gopal Energy |
Suman Sarwari HEP, HP |
5 |
18 |
M/s Himachal Hydel Projects (P) Ltd. |
Kurhed HEP, Chamba, HP |
5 |
19 |
M/s Nuziveedu Seeds Ltd, |
Masli HEP, Rohru, HP |
5 |
20 |
M/s Ginni Global Ltd. |
Balsio HEP, Chamba, HP |
5 |
21 |
Narmada Valley Development Authority |
Omkareshwar HEP, MP |
5 |
22 |
M/s Regency Yamuna Energy Ltd. |
Badyar HEP, Uttaranchal |
5 |
23 |
M/s Triveni Engineering & Industries Ltd. |
Joiner HEP, Chamba, HP |
5 |
24 |
M/s Kapil Mohan & Associates Hydro Power Private Limited. |
Beas Kund HEP, HP |
5 |
25 |
M/s Manglam Energy Development Co. P. Ltd |
Palor II, HP |
4.5 |
26 |
M/s DLI Power (India) Private Limited, |
Sechi HEP, Shimla, HP. |
4.5 |
27 |
M/s DLI Power (India) Private Limited, |
Melan HEP, Kinnaur, HP |
4.5 |
28 |
M/s Kapil Mohan & Associates Hydro Power Private Limited. |
Jirah HEP, HP |
4 |
29 |
M/s DLI Power (India) Private Limited, |
Panvi HEP, Kinnaur, HP |
4 |
30 |
M/s Himachal Hydel Projects (P) Ltd. |
Tulang HEP, Chamba, HP |
3 |
31 |
M/s Coastal Projects (P) Ltd.
Hyderabad |
Veligonda Irrigation Tunnel project, Prakasham Distt., AP |
|
|
ICCS HAS SUCCESSFULLY COMPLETED THE PFR & DPR WORKS FOR THE FOLLOWING PROJECTS:
S.No |
Project Developer |
Project |
Capacity in MW |
1 |
M/s Bhilwara Energy Ltd. |
Nyamjung Chhu HEP, Tawang, Arunachal Pradesh |
900 |
2 |
M/s RSWM Ltd. |
Allain Duhangan HEP, Kullu, HP |
192 |
3 |
M/s Green Ventures Private Limited |
Likhu HEP, Nepal |
120 |
4 |
M/s Jal Power corporation Ltd. |
Rangit IV HEP, Sikkim |
120 |
5 |
M/s Nuziveedu Seeds Ltd, |
Tidong-I HEP, Distt. Kinnaur, HP |
100 |
6 |
M/s RSWM Ltd. |
Malana HEP, Kullu, HP |
86 |
7 |
M/s Bhilwara Energy Ltd. |
UBDC Stage-III, Gurdaspur, Punjab |
85 |
8 |
M/s Krishna Knitwear |
Mori Hanol, Uttarakhand |
63 |
9 |
M/s Gammon Infrastructure projects Ltd. |
Rangit II HEP, Sikkim |
60 |
10 |
M/s Sunflag Power Ltd. |
Hanol Tuini HEP, Uttarakhand |
60 |
11 |
M/s Sobra Power Ltd |
Harsar HEP, Chamba, HP |
60 |
12 |
M/s Balephi Jal Vidyut Company Limited |
Balephi HEP, Nepal |
50 |
13 |
M/s Sobra Power Ltd |
Bharmour HEP, Chamba, HP |
45 |
14 |
M/s Electrosteel Castings Limited |
Balason HEP, West Bengal |
24 |
15 |
M/s Signet Suppliers Private Limited. |
Kut HEP, HP |
24 |
16 |
M/s Kanchanjunga Power Co. Pvt. Ltd. |
Baragaon HEP, Kullu, HP |
24 |
17 |
M/s Polyplex Corporation Ltd. |
Bhilangana HEP, Uttarakhand |
24 |
18 |
M/s Norlha Associates (for Bhutan Power Corporation) |
Begana HEP, Bhutan |
20 |
19 |
M/s Choudhary Power Projects |
Ranja-Ala-Dunadi HEP. J&K |
15 |
20 |
M/s Harsil Hydro Ltd. |
Jalandhari HEP, Uttarakhand |
15 |
21 |
M/s Uttar Bharat Hydro (P) Limited |
Sarju II HEP, Uttarakhand |
15 |
22 |
M/s Uttaranchal Infrastructure Projects Co. Pvt. Limited. |
Bawas Dam, Kosi Valley, Uttarakhand |
13 |
23 |
M/s Harsil Hydro Ltd. |
Kakora HEP, Uttarakhand |
12 |
24 |
M/s Harsil Hydro Ltd. |
Siyan HEP, Uttarakhand |
10 |
25 |
M/s Sulzer flovel Hydro Ltd. |
Hemavathy HEP, Karnataka |
8 |
26 |
M/s P & R |
Brenwar, Jammu & Kashmir |
7.5 |
27 |
M/s Ginni Global Ltd. |
Taraila HEP, Chamba, HP |
5 |
28 |
M/s Ginni Global Ltd. |
Balsio HEP, Chamba, HP
|
5 |
29 |
M/s Tarini Hydro power Company (P) Ltd. |
Kurpan HEP, Rampur, HP |
5 |
30 |
M/s DLI Power (India) Private Limited, |
Rajpur HEP, Rampur, HP |
4.5 |
31 |
M/s DSCL, New Delhi |
Bathad HEP, Kullu, HP |
4.5 |
32 |
M/s Modi Power (P) Ltd. |
Upper Manglad, Shimla, HP |
4.5 |
33 |
M/s DSCL, New Delhi |
Banagi HEP, Kullu, HP |
4 |
34 |
M/s DSCL, New Delhi |
Farari HEP, Kullu, HP |
3.5 |
35 |
M/s Global Corporation |
Durghed HEP, Chamba, HP |
2 |
36 |
M/s Global Corporation |
Kiri HEP, Chamba, HP |
1.5 |
27 |
M/s RSWM Ltd. |
Kala HEP, Kullu, HP |
1.5 |
38 |
M/s Ajay Energy |
Dogri HEP, Rohru, HP |
1.1 |
|
ICCS IS CURRENTLY WORKING ON THE COMPLETION OF PFR & DPR WORKS FOR THE FOLLOWING PROJECTS:
S.No |
Project Developer |
Project |
Capacity in MW |
1 |
M/s Uttaranchal Infrastructure Projects Co. Pvt. Ltd. |
Alaknanda Valley |
600 |
2 |
M/s Bhilwara Energy Ltd. |
Angoline HEP, Arunachal Pradesh |
375 |
3 |
M/s Bhilwara Energy Ltd. |
Malinye HEP, Arunachal Pradesh |
335 |
4 |
M/s Malana Power Company Ltd. |
Barabangahal HEP, HP |
200 |
5 |
M/s Bhilwara Energy Ltd. |
Chango Yangthang HEP, HP |
140 |
|
ICCS IS CURRENTLY RENDERING PRE-TENDER ENGINEERING SERVICES FOR THE FOLLOWING PROJECTS:
S.No |
EPC Contractor |
Project |
Capacity in MW |
1 |
M/s Patel Engineering Ltd. |
Vishnugad Pipalkoti |
444 |
2 |
M/s Patel Engineering Ltd. |
Kishanganga HEP |
330 |
3 |
M/s Hindustan Construction Co. Ltd. |
Rupsiabagar Khasiabara HEP |
261 |
4 |
M/s Patel Engineering Ltd. |
Lata Tapovan HEP |
172 |
5 |
M/s Hindustan Construction Co. Ltd. |
Rammam HEP
|
120 |
6 |
M/s Hindustan Construction Co. Ltd. |
Sainj HEP |
100 |
7 |
M/s Coastal Project Private Ltd. |
Broadlands HEP |
36 |
8 |
M/s Hindustan Construction Co. Ltd. |
Kanthalapalli Dam |
- |
|
ICCS HAS COMPLETED THE DUE DILIGENCE STUDIES FOR THE FOLLOWING PROJECTS:
S.No |
Name of the Project |
Tentative installed capacity in MW |
HIMACHAL PRADESH |
1 |
Jangi Thopan |
480 |
2 |
Thopan Parwari |
480 |
3 |
Reoli/Dugli |
420 |
4 |
Seli |
320 |
5 |
Youngthang Khab |
261 |
6 |
Kutehr |
240 |
7 |
Gyspa |
240 |
8 |
Dugar |
236 |
9 |
Bara Bangahal |
200 |
10 |
Bajoli Holi |
180 |
11 |
Tandi |
150 |
12 |
Rashil |
150 |
13 |
Sach-Khas |
149 |
14 |
Gondhala |
144 |
15 |
Chango Youngthang |
140 |
16 |
Sumte Kothang |
130 |
17 |
Bardang |
114 |
18 |
Chhatru |
108 |
19 |
Lara Sumta |
104 |
20 |
Miyar |
90 |
21 |
Tinget |
81 |
22 |
Mane Nadang |
70 |
23 |
Teling |
61 |
24 |
Patam |
60 |
25 |
Lara |
60 |
26 |
Ropa |
60 |
27 |
Kuling Lara |
40 |
28 |
Rupin |
39 |
29 |
Chanju-I |
25 |
30 |
Chanju-II |
17 |
31 |
Bharari |
5.5 |
ARUNACHAL PRADESH |
32 |
Nyamjang Chuu HEP |
900 |
33 |
Angoline HEP |
375 |
34 |
Malinye HEP |
335 |
NEPAL |
35 |
Humla Karnali- i |
274 |
36 |
Mugu Karnali- i |
194 |
38 |
Karnali- iv |
166 |
39 |
Likhu HEP |
120 |
40 |
Upper Seti |
80 |
41 |
Dudhkoshi- v |
64 |
42 |
Loti karnali |
51 |
43 |
Upper Dudhkoshi |
50 |
44 |
Balephi HEP |
50 |
|
ICCS HAS DONE THE RMU’s / LE STUDIES FOR THE FOLLOWING PROJECTS:
S.No |
Project Developer |
Project |
Capacity in MW |
A. RMU’s Studies |
1 |
M/s Tamil Nadu Electricity Board |
Sholayar –I |
180 |
2 |
M/s Tamil Nadu Electricity Board |
Priyar |
140 |
3 |
M/s Tamil Nadu Electricity Board |
Kodayar –II |
40 |
4 |
M/s Tamil Nadu Electricity Board |
Sholayar –II |
25 |
5 |
M/s Sulzar Hydro |
Bhandardara HEP
Maharashtra |
12 |
B. Lender’s Engineers |
6 |
ICICI Bank |
Hemavathy Project Karanataka |
16 |
|
ICCS HAS DONE THE DESIGNING OF TRANSMISSION LINE & SUB-STATIONS FOR THE FOLLOWING PROJECTS:
S.No |
Project Developer |
Project |
1 |
M/s HEG |
132 kV Outdoor Receiving Sub-station at Mandideep, M.P. |
2 |
M/s Malana Power Company Ltd. |
132 kV Outdoor Generating Sub-station at Malana HEP, H.P. |
3 |
M/s A D Hydro Power Ltd. |
220 kV Outdoor Generating Sub-station at Allain-Duhangan HEP, H.P. |
4 |
M/s Himachal Pradesh State Electricity Board |
400/ 220/ 132 kV Receiving Sub-station at Kunihar |
5 |
M/s Himachal Pradesh State Electricity Board |
400 kV, 35 km Single Circuit Transmission Line from Kunihar to Nalagarh, HP. |
6 |
M/s HEG |
33 kV Indoor Receiving Sub-station at Mandideep, M.P. |
7 |
M/s HEG |
33 kV Outdoor Receiving Sub-station at Mandideep, M.P. |
8 |
M/s HEG |
33 kV Outdoor Generating Sub-station at Tawa HEP, M.P. |
9 |
M/s Reliance Energy Ltd. |
26 Nos. 220/132/66/33/11 kV GIS and Conventional Substations at Delhi & Mumbai |
10 |
M/s Malana Power Company Ltd. |
132 kV, 25 km Double Circuit Transmission Line from Malana to Bajaura, H.P. |
11 |
M/s A D Hydro Power Ltd. |
220 kV, 175 km Double Circuit Transmission Line from Allain Duhangan to Nalagarh, HP |
|
|
|
|
|
|
|
|